Bangladesh Ghorashal Unit 4 Repowering Project
一句话结论
这是一个位于孟加拉国的能源类海外投资项目,当前阶段为已关闭,批准金额 2.2 亿美元,批准日期 2015-12-21,由国际多边开发机构提供资金。项目编号 P128012。
免费注册智商号,开通套餐看全海外项目信息 · 年底促销 ¥299/两年(买一年送一年)
免费注册智商号关键事实
- 国别 / 地区
- 孟加拉国(Bangladesh)
- 行业
- 能源
- 项目阶段
- 已关闭
- 批准金额
- 217,000,000 美元(约 2.2 亿美元)
- 批准日期
- 2015-12-21
- 项目编号
- P128012
- 资金来源
- 国际多边开发机构
- 数据来源
- 百云数据整理入库
项目摘要
The development objective of the Ghorashal Unit Four Repowering Project is to increase generation capacity and efficiency of the targeted power plant. There are two components to the project, the first component being re-powering of the target unit. His component will finance all the required plant equipment and auxiliaries, design and installations services for the full repowering of unit four. The major plant equipment include a new Gas Turbine and Generator (GTG), a Heat Recovery Steam Generator (HRSG), Distributed Control System (DCS), gas booster compressor, main stack, bypass stack and all other associated ancillary equipment. The works will include complete overhauling of the existing ST generator, replacement and modernization of the existing auxiliaries, rehabilitation and modernization of existing cooling towers and workshop buildings, construction of a regulatory metering station (RMS), dismantling of the existing boiler, and construction of residential and non-residential buildings. Finally, the second component is the technical assistance for institutional strengthening support. This component would finance an owner’s Engineer (implementation support consultant) for the Project to bolster project governance while ensuring effective management, monitoring and quality assurance of the design, engineering and construction and the initial operation of the repowered plant. This component would also focus on capacity building and institutional support to operate the plant effectively and efficiently as well as support BPDB to help strengthen its technical and managerial capacity to plan, develop and operate its generation portfolio.
项目编号 P128012 · 入库编号 972612bb5c43
同国别其他在执行项目
| 项目名称 | 金额 | 批准日期 |
|---|---|---|
| Chattogram Water Supply Improvement Project | 2.8 亿美元 | 2024-12-19 |
| Health, Nutrition and Population Sector Development Program | 3.8 亿美元 | 2024-12-19 |
| Second Bangladesh Green and Climate Resilient Development Credit | 5.0 亿美元 | 2024-12-19 |
| Bay Terminal Marine Infrastructure Development Project | 6.5 亿美元 | 2024-06-28 |
| Bangladesh Second Recovery and Resilience DPC | 5.0 亿美元 | 2024-06-21 |
同行业其他项目
- Third Fiscal Consolidation, Sustainable Energy & Competitiveness DPF 2017-12-05
- Energy Efficiency Development Policy Loan 2011-06-07
- EQUITABLE AND GREEN RECOVERY DEVELOPMENT POLICY FINANCING 2022-03-24
- Power Sector Recovery Performance Based Operation 2020-06-23
- Romania Second Programmatic Inclusive and Green Growth Development Policy Loan 2023-06-30