Nurek Hydropower Rehabilitation Project Phase 2
一句话结论
这是一个位于塔吉克斯坦的能源类海外投资项目,当前阶段为在执行,批准金额 5000 万美元,批准日期 2020-06-26,由国际多边开发机构提供资金。项目编号 P173804。
免费注册智商号,开通套餐看全海外项目信息 · 年底促销 ¥299/两年(买一年送一年)
免费注册智商号关键事实
- 国别 / 地区
- 塔吉克斯坦(Tajikistan)
- 行业
- 能源
- 项目阶段
- 在执行
- 批准金额
- 50,000,000 美元(约 5000 万美元)
- 批准日期
- 2020-06-26
- 项目编号
- P173804
- 资金来源
- 国际多边开发机构
- 数据来源
- 百云数据整理入库
项目摘要
The objective of the Second Phase of Nurek Hydropower Rehabilitation Project for Tajikistan is to rehabilitate and increase the generating capacity of six power generating units of Nurek Hydropower plant (HPP) and improve their efficiency. The project has two components. Component 1: Rehabilitation of six generating units and related penstocks, and strengthening of Nurek HPP capacity to operate and maintain the power plant will consist of two sub-components. Sub-component 1.1: Rehabilitation of six generating units will finance: (a) rehabilitation of six power generating units, including generators, turbines, main inlet valves, and transformers, and supply of spare parts to ensure sustainable operation of rehabilitated units; and (b) rehabilitation of penstocks related to six units to be rehabilitated. Sub-component 1.2: Rehabilitation of Nurek bridge, the powerhouse, and other building and strengthening of Nurek HPP capacity to operate and maintain the power plant will finance: (a) rehabilitation of Nurek bridge; (b) rehabilitation of the powerhouse and some other buildings/structures at Nurek HPP that may require rehabilitation; and (c) purchase of machinery, including excavators, forklift trucks, truck cranes, required for maintenance of the power plant. Component 2: Technical assistance will support implementation of the project and strengthen the institutional capacity of Barqi Tojik (BT) by supporting the following. (a) Additional Project Management Consultant (PMC) costs that may be required to assist BT with the review of designs, bidding, quality control and construction supervision of the project. (b) Technical, economic, financial, and other studies, which may be required during Project implementation, including, but not limited to hydrologic risk study for the Tajik hydro-dominated energy sector to quantify the financial impact of the dry years and other climate shocks and design financial mitigation tools to reduce vulnerability and introduce climate resilience in the sector. (c) Consultant services to support BT with citizen engagement, carrying out of gender-informed consultative processes during project implementation, and promotion of larger participation of women in the workforce of BT. (d) Capacity building for Nurek HPP, Ministry of Energy and Water Resources (MEWR), and BT staff in dam safety, operation and management of hydro facilities, project management, procurement, financial management, and good practices of ensuring compliance and managing the E and S aspects of the Project. (e) Project and entity audits. (f) Incremental operating costs of the project implementing entity. Moreover, the Phase 2 of the project will be supporting a hydrological risk study to estimate the impact of changes in hydrological conditions on the financial standing of BT.
项目编号 P173804 · 入库编号 e47df0c54e32
同国别其他在执行项目
| 项目名称 | 金额 | 批准日期 |
|---|---|---|
| Tajikistan Digital Foundations Project | — | 2024-12-17 |
| Sustainable Financing for Rogun Hydropower Project | 3.5 亿美元 | 2024-12-17 |
| Tajikistan Millati Solim Project | 4000 万美元 | 2023-10-24 |
| Financial and Private Sector Development Project | 5000 万美元 | 2023-07-10 |
| Social Protection Modernization and Economic Inclusion Project | 3500 万美元 | 2023-03-24 |
同行业其他项目
- First Low-Carbon Energy Programmatic Development Policy Loan 2023-06-29
- Second Additional Financing for Dasu Hydropower Stage I Project 2024-06-10
- Tarbela Fourth Extension Hydropower Project 2012-03-20
- Vishnugad Pipalkoti Hydro Electric Project 2011-06-30
- Pumped Storage Technical Assistance Project 2011-05-26
引用本条请注明:中项目信息网(cproject.net),数据由百云数据整理入库, 页面更新于 2026-11-25。